The final 14-tonne and 20-tonne bridge beams for the new A1 connection to the B1174 were lifted into place in February.
What we achieved in February
- Installed the final 14-tonne and 20-tonne bridge beams for the new A1/B1174 connection
- Carried out essential site clearance works to the A1
- Continued steel and concrete works to the new A1/B1174 connection
- Started laying road surfacing at the eastern roundabout
- Continued earthworks across site, particularly at western end of the scheme
- Continued Phase Three Anglian Water watermain diversion and BT ducting
- Continued post-excavation archaeological reporting
What's happening in March
- Pour concrete for the new bridge connecting the A1/B1174
- Continue drainage works and earthworks across the entire site
- Start kerb installation at the western roundabout
- Continue Phase Three Anglian Water watermain and sewer diversions
- Continue post-excavation archaeological reporting
Upcoming traffic restrictions and closures
- None
Current/ongoing traffic restrictions and closures
- 50mph speed limit and narrowed lanes on the A1 between Harlaxton to Little Ponton