Peppermint Junction update: Project to complete three months ahead of schedule

6 December 2017

The £5.4m project to improve safety at the A17/A151 junction is to complete in December, three months ahead of schedule and within budget.  

Three months ahead of schedule

Three months ahead of schedule

What we achieved in November

  • Completed final carriageway surfacing to A17 and A151 and laid white lines and road studs
  • Continued footway and splitter island surfacing
  • Completed street lighting installation
  • Installed road signs and bollards
  • Completed drainage works
  • Topsoiling to verges and roundabout islands.
  • Fully opened the A17 roundabout to traffic
  • Resurfaced and added a merge-in lane on the A17 (east of B1168 roundabout) for eastbound traffic

What’s happening in December

  • Carry out landscaping on verges and roundabout islands, as well as planting vegetation
  • Complete any outstanding minor works
  • Remove project site cabins and compound

Current traffic restrictions and closures

  • Reduced lane widths for some remaining activities; however, two-way traffic flow will remain unaffected
  • Northon’s Lane will remain permanently closed at the junction with the A151
  • Temporary 30mph speed restriction will remain in force until the end of the works on Friday 8 December

For the latest news on the Peppermint Junction, visit


Did you find what you were looking for?

Please give us your name, email address and any comments you have.

Last updated: 6 December 2017

Bookmark with:

What are these?


Powered by Webstructure.NET