Lincoln Eastern Bypass

The A15 Lincoln Eastern Bypass is a 7.5km road designed to improve Lincoln’s infrastructure, encourage growth, minimise traffic congestion and enhance the inter-city environment.

3D fly-thorough

Works started on-site on 6 December 2016 when Network Rail began construction of a new railway bridge adjacent to Washingborough Road, which will allow the new road to run under the railway. See the project timeline for a full list of past and future milestones.

When complete, the bypass will start at a new roundabout on the A15 Sleaford Road and finish at the A158 Wragby Road, connecting with the existing northern relief road and becoming the next step towards creating a complete ring road around the city.

The bypass is being built by UK firm Carillion Construction and will see new roundabouts built at Greetwell Road, Washingborough Road, Lincoln Road, Branston and the A15 Sleaford Road.

The project is backed by Lincolnshire County Council, the Department for Transport, and the three district authorities (City of Lincoln Council, West Lindsey and North Kesteven District Councils).

Aims and benefits

  • Support Lincoln’s growth, in terms of economy and development
  • Reduce congestion in and around Lincoln, including a predicted  25% reduction on Broadgate
  • Enhance the inter-city environment
  • Open up land for new housing
  • Reduce carbon emissions
  • Improve air and noise quality
  • Form the penultimate step towards creating a complete ring road around the city of Lincoln
  • Incorporate a future-proofed design, where possible, so that dualling of the bypass can be considered in the future   

Cost and funding

The bypass will cost in the region of £99 million with £50m of central government funding, £15m from LCC and £34m from third party developers.

The third party developer’s costs will be forward-funded by the county council as they will take several years to recover, depending on the speed that houses are built.

Planning permission and public consultation

As a result of receiving £50m provisional funding from Central Government in 2011, a planning application for a single carriageway bypass was granted on 10 June 2013, with an update in October 2014.

A public inquiry took place from 11-21 August 2015 to again consider the cases for and against the legal orders. On 16 February 2016, the council was granted the Compulsory Purchase Orders and Side Road Orders by the Secretary of State for Transport.

Timeline

DateDescription
Dec 2012Planning permission submitted
Jun 2013Planning permission granted
Aug 2015Public inquiry takes place
Feb 2016Legal Orders granted by Secretary of State
May 2016Contractors arrive on-site to build 130m track for access
Sep 2016Archaeologists arrive on-site
Nov 2016Funding confirmed by Department for Transport
Dec 2016Network Rail begins work to build a railway bridge over the line of the new bypass
Jun 2017Main construction works begin
Jul 2017Work on Market Rasen line rail bridge begins
Oct 2017Network Rail Lincoln to Spalding Railway underbridge slid into place during 72-hour rail closure
Apr 2018 *Washingborough railway bridge complete
Oct 2018 *Lincoln Road underpass complete
Nov 2018 *Access to and from Cherry Willingham via Hawthorn Road ends
Nov 2018 *Bloxholm Lane footbridge complete
Jan 2019 *Greetwell Road Roundabout complete
Feb 2019 *Hawthorne Road NMU bridge complete
Mar 2019 *Greetwell Road footbridge complete
Mar 2019 *Heighington Road bridge complete
Apr 2019 *Lincoln Road Roundabout complete
Jul 2019 *Sleaford Road Roundabout complete
Aug 2019 *Lincoln to Market Rasen railway bridge complete
Aug 2019 *River Witham Viaduct complete
Sep 2019 *Washingborough Road Roundabout complete
Oct 2019 *Bypass available to traffic
Win 2019 *Project officially complete

*All future dates are projected and subject to change dependant on external factors.

Downloads

The following files will open in their associated programs.
To view PDF files on our website Adobe Acrobat Reader 5 or above is recommended. To upgrade for free visit the Adobe website

For help with reading pdf files please visit the Adobe Acrobat Access site

Roadworks map

Roadworks being carried out by all local authorities and utility companies.

www.roadworks.org

Videos

View all Lincolnshire Eastern Bypass videos published to date.

More info...

Photographs

View photographs of the Lincoln Eastern Bypass as it is constructed.

More info...

Archaeology

Find out about the archaeological investigations and findings so far.

More info...

News: Lincoln Eastern Bypass

Lincoln Eastern Bypass

Council looking into all options following Carillion liquidation announcement

15 January 2018 | Updated: 15 January 2018

County council officials are determining the best way forward following the announcement that its primary Lincoln Eastern Bypass contractor, Carillion, has gone into liquidation following struggles with debts of £900m.

Drone photo of LEB site

Lincoln Eastern Bypass update – New Year works include bridge supports and topsoil stripping

2 January 2018 | Updated: 9 January 2018

Work continues to progress with archaeological investigations and bridge works as soil-stripping begins along the River Witham, signifying the start of main construction works.

Lincoln eastern bypass artist impression

Greetwell Fields Lane to close next month, making way for Lincoln Eastern Bypass

13 December 2017 | Updated: 9 January 2018

The road, locally known as the Bunny Run, will be permanently closed from mid January 2018.

Eastern bypass piling works for Greetwell rail bridge underway

Lincoln Eastern Bypass update – Market Rasen Rail Bridge works progress as project team moves into Washingborough office Video

1 December 2017

Archaeological investigations and Washingborough rail bridge works are nearing an end, with main construction works along the route ready to ramp up in the New Year.

Road Closed

Heighington Road and Bloxholm Lane road closures planned for later this month

2 November 2017 | Updated: 16 November 2017

The closures will allow Carillion to install new underground ducting across the carriageway as part of the Lincoln Eastern Bypass construction.

View All



Did you find what you were looking for?

Please give us your name, email address and any comments you have.

Last updated: 1 December 2017

Bookmark with:

What are these?

 
 

Powered by Webstructure.NET