Detail design for roads and footpaths

10. Traffic signals

All traffic signal equipment shall be supplied and installed by us. This is to ensure that the equipment is compatible with existing traffic management control systems, monitoring equipment, associated systems database programming and validation. This will also ensure that equipment is to the correct specification and can be included in existing maintenance regimes.

We will provide a quotation for the supply and installation. Full payment shall be made prior to commencement of works to allow procurement of the required equipment.

A minimum of 16 weeks shall by required between placing the order and installation of equipment in the public road. This lead in time should be factored into works programmes.