Total spend - agency or contract staff working in project management, programme management, PMO, business change or ICT infrastructure roles broken down by supplier or agency.

Request

1. Total spend in the last complete financial year on interim, agency or contract staff working in project management, programme management, PMO, business change or ICT infrastructure roles broken down by supplier or agency where that is held.

 
2. The number of such interim or contract workers engaged at the date of this request, by role type.

 
3. The name of any framework, agency agreement or managed service provider through which those workers are engaged.

 

Decision

1.

Company Amount
Castlefield Recruitment Limited (Permanent) £62,101
SThree Partnership LLP t/a Computer Futures £62,101
INFOJAM Limited £15,120
Matrix £64,355
Total £178,831

 

2. None at the date the request was made

 

3. ESPO MSTAR 3

Reference number
18306857
Date request received
07/10/2026
Date of decision
14/10/2026