Lincolnshire Highways Contract with Balfour Beatty Living Places - Find a freedom of information request

Request

Details in respect of the contract below:

1. Lincolnshire Highways Contract with Balfour Beatty Living Places:

Contract Data Part 1 specifically including: the Secondary Option Clauses selected; the Pain/Gain share percentages and ranges and the breakdown of the X clauses with specific reference to X17 and X20.

Decision

I can confirm that the information requested is held by Lincolnshire County Council. I have detailed below the information that is being released to you. 

 

1. The chosen secondary options are

X1, X2, X9, X10, X12, X15, X16, X17, X18, X21, X23, X24, Y(UK)2, Y(UK)3, Z (X9 and X15 have been taken from NEC4 ECC, X16 has been taken, but modified, from NEC4 ECC)

The Contractor’s share percentages and the share ranges are:

Share range                  Contractor’s share percentage

Less than 95 %               Nil %

From 95 % to 105 %     50 %

Greater than 105 %     100 %

For Clause X17 see attached

Clause X20 is not used

Should you require the attachment mentioned above please contact customerinformationservice@lincolnshire.gov.uk with the below reference number and this can be provided.

 

Reference number
FOI 11725061
Date request received
11/02/25
Date of decision
06/03/25