Following our previous FOI, we are interested in job number 4703088.
As we understand it, the work seems to have started on 28 February 2019 and completed on the 19 October 2020 at Goltho Road. It is considered as location 17/15/26/BR-APLEY CULVERT.
1. Can you please confirm that our understanding as to the timescales are correct.
2. Could you also please indicate precisely by reference to providing us with a map, as to where this work was carried out.
3. We also specifically need to know whether this was subject to a road closure during the dates that we have identified above. - Decision
-
1. The job was raised on the 28th February 2019 and cancelled 19th October 2020, with no physical works taking place
2. Please find attached map
3. Works cancelled, no traffic management of any sort erected.
Further to the requested information, these planned works were to repoint brickwork and clear vegetation on the bridge headwalls, and were not in relation to any surfacing defect. They do not relate to a hazard to road users, rather to the ensuring the culvert remains in good structural condition in the long-term
Should you require the attachment mentioned above please contact customerinformationservice@lincolnshire.gov.uk with the below reference number and this can be provided.
- Reference number
- FOI 12165473
- Date request received
- 09/04/25
- Date of decision
- 30/04/25