- Request
-
Q1) Please can I have information on the progress of the Grantham Southern Relief Road. The project has been ongoing for 10 years. I understand there have been design errors - twice. However the town is full of traffic all of the time, the relief road is needed urgently.
Q2) Please provide an update on timescales for completion, and confirmation that the previous bridge errors have been rectified. - Decision
-
I can confirm that the information requested is held by Lincolnshire County Council. I have detailed below the information that is being released to you.
1.Thank you for raising your concerns regarding the delivery of the Grantham Southern Relief Road. We regularly update the Grantham Southern Relief Road webpage with the latest project information, including the proposed completion date and regular progress updates. You can access it here: Grantham Southern Relief Road – About the project - Lincolnshire County Council
2.The bridge design issues are well documented and summarised on the webpage. I can confirm that the designers are actively working through the redesign of the bridge launching process, with the aim of achieving the revised programme.
The Council are actively working towards the planned programme to deliver the GSRR project and provide regular updates on the webpage, as these become available, but at present the Council cannot confirm when the bridge redesign will be complete and installed as we do not hold this information.
- Reference number
- 12575481
- Date request received
- 2 June 2025
- Date of decision
- 23 June 2025