LEVI (Local Electric Vehicle Infrastructure) funding

Request

1. The total LEVI (Local Electric Vehicle Infrastructure) funding allocated to your council and the amount spent to date. 

2.The total number of EV chargepoints installed to date using LEVI funding (please provide type if available). 

3.The total number of additional chargepoints currently planned or contracted for installation under this funding, and the expected delivery timeline. 

4. Does the council have plans to run cross-pavement charging trials to help residents without driveways safely charge their electric vehicles? 

Decision

I can confirm that the information requested is held by Lincolnshire County Council. I have detailed below the information that is being released to you.

1. LEVI Pilot:

Allocated – £248,520.60

Spend to date – £49,704.12

LEVI Capital Fund:

Allocated – £5,620,000

Spend to date – £0

2. Zero

3. LEVI Pilot – 55 charge points

LEVI Capital Fund – The exact number of charge points to be installed under this funding is subject to the outcomes of an ongoing procurement exercise

4. Lincolnshire County Council currently has no plans to run cross-pavement charging trials, however are actively reviewing the results of trials conducted elsewhere by other local authorities.

Reference number
FOI 13329905
Date request received
06/08/25
Date of decision
04/09/25