Final surfacing to be laid at A52 Somerby Hill roundabout.
What we achieved in May
Phase Two
- Carried out southbound drainage, street-lighting verge works on the A1
- Final drainage and landscaping works across site
- Surfacing to new link roads and roundabouts
Phase Three
- West side of site – completed piling at pier 3
- East side of site – surfacing from Whalebone Lane to Somerby Hill / continue rock processing and main road excavation / carried out additional ground investigation works at east embankment / continued drainage, ducting and kerbing works at Somerby Hill roundabout
What's happening in June
Phase Three
- East side of site – complete rock processing and main road excavation / lay surfacing at Somerby Hill roundabout / drainage works at new mid-route roundabout
Current/ongoing traffic restrictions and closures
- Ongoing lane closures on the B1174 roundabout until the end of the scheme
- Temporary traffic signals and lane closures as needed at Somerby Hill Roundabout
Upcoming traffic restrictions and closures
- From 6th June for up to three weeks – full 24/7 closure of the B1176 and B6403 Somerby Hill roundabout legs; other legs will operate under temporary traffic signals
- B1176 diversion route via B6403 / A151 / B1193 / A15 / A52, and vice versa
- B6403 diversion route via B1176 / A1 / B1174 / A52, and vice versa
- Between 20th June and 1st July – night-time closure of the A52 Somerby Hill roundabout legs from 8pm to 6am for 5-7 evenings
- Diversion routes via all of the following (on-route signage will be in place directing traffic to their specific destination):
- A52 / A607 / A153 / A15 / A52, and vice versa
- A52 / A15 / B1193 / A151 / B6403, and vice versa
- A52 / B1174 / A1, and vice versa
- Diversion routes via all of the following (on-route signage will be in place directing traffic to their specific destination):