Waddington road surfacing improvements set for late July

Waddington resurfacing

Works to replace worn out carriageway on several Waddington roads will start in late July.


Phase 4 of Waddington road surfacing to start next week - 08/09/2022

Please be aware that the Phase 4 resurfacing works, originally planned to start earlier this week in Waddington, will begin on Monday 12 September.

Below is an update to phases 4 and 5:

  • Phase 4 – Hill Top / Tinkers Lane – Monday 12 September for up to three weeks
    • Night-time road closure of Hill Top / Tinkers Lane (from Hill Top at the Staples Lane bell mouth to Tinkers Lane junction with A607), 7pm to 6am
      • Diversion via: south on A607 / west on Church Lane, Hill Top and Station Road / north on Low Road / north on Brant Road / south on Station Road, and vice versa
  • Phase 5 – Brant Road surfacing – Monday 3 October for four weeks
    • Night-time road closure of Brant Road (from Palm Road / Boundary Stores to Station Road), 7pm to 6am
      • Diversion via: Hill Top Road / Hill Top & Tinker Lane / north on A607 to Lincoln / south on Newark Road, and vice versa

Waddington road surfacing date changes - 10/08/2022

Please note that the phasing for the ongoing Waddington road resurfacing works has changed slightly.

Updated programme below. All dates and times are subject to suitable weather.

  • Phase 3 – Brant Road footways – Monday 8 August for up to seven weeks
    • Temporary traffic signals during the day between 9:30am and 7pm
  • Phase 4 – Hill Top / Tinkers Lane – Monday 5 September for up to three weeks
    • Night-time road closure of Hill Top / Tinkers Lane (from Top Road at the Staples Lane bell mouth to Tinker Lane), 7pm to 6am
      • Diversion via: south on A607 / west on Church Lane, Hill Top and Station Road / north on Low Road / north on Brant Road / south on Station Road, and vice versa
  • Phase 5 – Brant Road surfacing – Monday 26 September for four weeks
    • Night-time road closure of Brant Road (from Palm Road to Station Road), 7pm to 6am
      • Diversion via: Hill Top Road / Hill Top & Tinker Lane / north on A607 to Lincoln / south on Newark Road, and vice versa

Waddington road surfacing improvements set for late July - 05/07/2022

The improvement project will start on Monday 25 July and last up to twelve weeks (subject to weather).

The project will be carried out in five phases. Below is a list of roads where sections of carriageway will be rebuilt:

  • Brant Road
  • Hollywell Road
  • Hill Top / Tinkers Lane
  • Far Lane
  • Manor Lane

Waddington Road Improvements Phasing Plan

Please note that all works will take place during weekday days / evenings only. All dates and times
are subject to suitable weather.

Phase 1 – Hollywell Road – Monday 25 July for one week

  • Daytime road closure of Hollywell Road (from the start of Hollywell Junction to Rowan Road Bus Stop), 9:30am to 7pm
    • Diversion via: south on Brant Road / east on Valley Road / north on Redwood Drive / east on Acacia Avenue / north on Hollywell Road, and vice versa
Diversion route Holywell Road Diversion route Holywell Road

Phase 2 – Far Lane and Manor Lane – Monday 1 August for up to 8 days

  • Daytime road closures, 9:30am to 7pm
    • All of Manor Lane, including the junction bell mouth on both sides
    • Far Lane, from Viking Close to Station Road
      • Diversion via: south on Hill Top Road / west on Tinkers Lane / north on High Street, and vice versa
Diversion route Far Lane Diversion route Far Lane
Diversion route Manor Lane Diversion route Manor Lane

Phase 3 – Brant Road footways – Monday 1 August for six weeks

  • Temporary traffic signals during the day between 9:30am and 7pm

Phase 4 – Brant Road surfacing – Tuesday 30 August for four weeks

  • Night-time road closure of Brant Road (from Palm Road to Station Road), 7pm to 6am
    • Diversion via: Hill Top Road / Hill Top & Tinker Lane / north on A607 to Lincoln / south on Newark Road, and vice versa
Diversion route Brant Road Diversion route Brant Road

Phase 5 – Hill Top / Tinkers Lane – Monday 26 September for up to three weeks

  • Night-time road closure of Hill Top / Tinkers Lane (from Top Road at the Staples Lane bell mouth to Tinker Lane), 7pm to 6am
    • Diversion via: south on A607 / west on Church Lane, Hill Top and Station Road / north on Low Road / north on Brant Road / south on Station Road, and vice versa
Diversion route Hill Top Tinkers Lane Diversion route Hill Top Tinkers Lane

Cllr Richard Davies, executive member for highways, said: "As many will have noticed, some of the roads in Waddington are nearing the end of their serviceable life. As a result, we'll be rebuilding them starting in July.

"This will be a massive improvement project. In fact, we expect to lay over 9,000 tonnes of new tarmac over the twelve-week scheme.

"Although there will inevitably be some disruption, we'll be doing everything we can to keep this to a minimum including maintaining access for residents throughout the entire scheme.”

Cllr Thomas Dyer, county councillor for Waddington and Hykeham East, said: “I’m thrilled that these essential works are set to start next month.

“With over 6,000 residents, Waddington is one of the county’s largest villages, and I think nearly everyone who lives in or travels through the area will be pleased to see us rebuilding sections of Brant Road, Hollywell Road and other key roads that are in desperate need of repair. 

“Residents will no doubt experience some inconvenience over the planned twelve weeks of work, but it’s important that we get these improvements completed as quickly as possible.

"As your local councillor, should anyone have any problems, please do not hesitate to contact me."

For up-to-date information about this and other roadworks, visit www.lincolnshire.gov.uk/roadworks

Published: 5th July 2022