Grantham Southern Relief Road August update

GSRR August Update

Phase Three works continuing ahead

What we achieved in July

Phase Two

  • Resurfacing works to northbound A1 Lane 2
  • Testing and commissioning of northbound and southbound streetlights on the A1

Phase Three

  • West side of site – pier 1 bases concreted / pier 2 reinforcement fixed / pier 3 cofferdam excavated / embankment construction materials stockpiled
  • East side of site – continued drainage, ducting and kerbing works at Somerby Hill roundabout / soakaways dug between Whalebone Lane and development / continued with rock processing operations

What's happening in August

Phase Three

  • West side of site – pier 2 bases concreted / pier 3 bases reinforcement fixed and concreted
  • East side of side – complete works at Somerby Hill roundabout / install filter drains and road box between Whalebone Lane and development / begin next set of ground investigation works

Current/ongoing traffic restrictions and closures

  • Ongoing lane closures on the B1174 roundabout until the end of the scheme
  • Temporary traffic signals and lane closures as needed at Somerby Hill Roundabout

Upcoming traffic restrictions and closures

  • N/A

Published: 2nd August 2022