UPDATE: Waddington road surfacing improvements extended

Waddington resurfacing

Phasing for the ongoing Waddington road resurfacing works has changed.


Final road closure will take place on Brant Road this evening - 25/11/2022

A final road closure will take place on Brant Road this evening to paint road markings on the newly-resurfaced section of carriageway.

The closure will be in place from 7pm to 6am. The contractor's plan is to start at the Waddington end of site and work towards town with a view to maintaining access to all properties and side roads as far as reasonably practicable.

Diversion route via Hill Top Road / Hill Top & Tinker Lane / north on A607 to Lincoln / south on Newark Road, and vice versa.


UPDATE: Waddington road surfacing improvements extended - 04/10/2022

The ongoing improvement project will be extended in order to increase the scope of the project and account for a series of unforeseen circumstances.

Under the extended scope, the Brant Road footways programme will now also look to improve driveways on the eastern side of the road.

Delays on other projects have had a knock-on effect and impacted on the availability of crews for this set of works.

Matched with some extreme weather, which delayed scheduled resurfacing works, this has extended some elements of the scheme by a number of weeks.

Karen Cassar, assistant director for highways, said:

“While it’s frustrating that we’ve had to extend these works due to several unforeseen circumstances, we’re glad to be able to undertake more improvement works than originally planned.

“By taking this opportunity to complete these additional improvements under an extended project, it saves residents from further works and disruption in the future.

“We’d like to thank everyone affected for their continued patience while we carry out the remainder of these works.”

The fully updated programme of works is as below. All dates and times are subject to suitable weather.

  • Phase 3 – Brant Road footways – Monday 1 August for up to fourteen weeks
    • Temporary traffic signals during the day between 7:30am and 7pm
  • Phase 4 – Hill Top / Tinkers Lane – Monday 12 September for up to five weeks
    • Night-time road closure of Hill Top / Tinkers Lane (from Station Road, 200m west of the Far Lane junction, to the Tinkers Lane junction with A607 Grantham Road), 7pm to 6am
      • Diversion via: south on A607 to Harmston / west on Church Lane, Hill Top and Station Road / north on Low Road / north on Brant Road / south on Station Road, and vice versa
  • Phase 5 – Brant Road surfacing – Monday 17 October for five weeks
    • Night-time road closure of Brant Road (from Palm Road to Station Road), 7pm to 6am
      • Diversion via: Hill Top Road / Hill Top & Tinker Lane / north on A607 to Lincoln / south on Newark Road, and vice versa
Diversion route Brant Road

Diversion route Brant Road

Diversion route Hill Top Tinkers Lane

Diversion route Hill Top Tinkers Lane

 

Published: 4th October 2022