Phase three is progressing well, with the west side embankment structural steelwork now complete.
What we achieved in January
Phase three
- West side of site – completed structural steelwork elements to piers / continued drainage works near the west embankment
- East side of side – continued surfacing between Whalebone Lane and development roundabout / completed excavation of east embankment back to the location of the new east abutment / carried out kerbing installation and surfacing at development roundabout / continued Pier 4 concreting works
What's happening in February
Phase three
- West side of site – continue concrete infills at Piers 1 and 2 / complete drainage to Pond B / continue drainage works near the west embankment
- East side of side – install main steelwork to Pier 4 / begin finishing works to development roundabout area verges / begin construction of working platforms for piling new elements of bridge / white lining along the newly-built road / complete surfacing between Whalebone Lane and development roundabout
Current/ongoing traffic restrictions and closures
- Lane Restrictions Around the B1174 Roundabout to facilitate the construction of the haul route and access into site
- Whalebone Lane closed
Upcoming traffic restrictions and closures
- N/A
For more information about the Grantham Southern Relief Road project, visit www.lincolnshire.gov.uk/gsrr.