What we achieved in November

Phase Three

  • West side of site – complete trestle launch foundations / begin steelwork assembly
  • East side of site – east abutment pile cropping / Pier 5 column concrete works / Pier 6 piling works

What's happening in December

Phase Three

  • West side of site – complete steelwork
  • East side of site – Pier 6 blinding (base layer of weak concrete or sand)  / east abutment reinforcement fixing and shuttering to initial pours; Pier 5 temporary structure foundations and construction

Current/ongoing traffic restrictions and closures

  • Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site

Upcoming traffic restrictions and closures

  • N/A