Grantham Southern Relief Road January 2024 update

Birds eye view of the progress on the Grantham Southern Relief Road

The latest updates for the Grantham Southern Relief Road.

What we achieved in December

Phase Three

  • West side of site – completed steelwork assembly
  • East side of site – Pier 6 blinding (base layer of weak concrete or sand)  / east abutment reinforcement fixing and shuttering to initial pour / Pier 5 temporary structure foundations and construction

What's happening in January

Phase Three

  • West side of site – install permanent and cantilever formwork / reinforce fixing on bridge deck
  • East side of site – Pier 6 reinforcement / east abutment  concrete works / reinforcement to wingwall bases / Pier 5 reinforcement and temporary structure decking

Current/ongoing traffic restrictions and closures

  • Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site

Upcoming traffic restrictions and closures

  • N/A

Published: 11th January 2024