Spalding Western Relief Road January 2024 update

Birds eye view of the progress of Spalding Western Relief Road

Latest updates for Spalding Western Relief Road.

What we achieved in October/November/December

  • Completed prep work so deck works can begin
  • Completed landscaping activities, including grass seeding and bulb planting
  • Installed the bridge beams onto the piers and abutments
  • Completed east and west diaphragm pours
  • Completed two deck pours
  • Completed ducting at Junction H
  • Installed badger culvert

What's happening in January/February/March

  • Complete settlement of and continue surcharge removal at the west junction and low height embankment
  • Install kerbing, drainage and street lighting at western junction
  • Continue construction of retaining wall
  • Continue construction of the bridge deck
  • Complete remaining deck pours

Current/ongoing traffic restrictions and closures

  • Closure of Two Plank Bridge and Blue Gowt Lane

Upcoming traffic restrictions and closures

  • Closure of public right of way 15/1 and Two Plank Lane for bridge footpath construction – starting 12th February until Summer 2024

Published: 11th January 2024