A16 Springfield Roundabout January update

A bird's eye view of the progress of the roundabout

Latest updates on the A16 Levelling Up Fund improvements.

What we achieved in December

  • Completed relocation of the 33kV electricity cables in the southwest corner
  • Installed temporary footway and started BT diversionary works to the northeast corner
  • Carried out site clearance in the southwest, northeast and west corners of the scheme
  • Completed drainage in the northeast corner

What’s happening in January

  • Completed earthworks in southwest corner of the roundabout
  • Kerbing, drainage, and earthworks in the northeast and southwest corner of the roundabout
  • Carriageway foundation layers of new widened sections of northeast and southwest corner excavated and constructed
  • Complete BT diversionary works in northeast corner of project
  • Construct headwalls in the northeast and southwest corner

Current/ongoing traffic restrictions and closures

  • 24/7 barriers at the roundabout, with the current two-lane entries and single-lane exits maintained
  • Ongoing narrowed roundabout lanes

Upcoming traffic restrictions and closures

  • N/A

Published: 17th January 2024