A16 Springfield Roundabout February update

An aerial view on the progress of the roundabout.

The latest update on the A16 Springfield Roundabout.

What we achieved in January

  • Continued earthworks in southwest corner of the roundabout
  • Started Kerbing, drainage, and earthworks in the northeast and southwest corner of the roundabout
  • Excavated and started construction of new widened sections of northeast and southwest corners of carriageway foundation layers
  • Completed BT diversionary works in northeast corner of project
  • Completed headwalls in the northeast and southwest corner

What’s happening in February

  • Complete construction of carriageway foundation in northwest and southeast corners
  • Complete kerbing and drainage in northwest and southeast corners
  • Start installing street lighting ducting and boxes
  • Finish earthworks in the northeast and southwest corners

Current/ongoing traffic restrictions and closures

  • 24/7 barriers at the roundabout, with the current two-lane entries and single-lane exits
  • Ongoing narrowed roundabout lanes

Upcoming traffic restrictions and closures

  • N/A

Published: 5th February 2024