Grantham Southern Relief Road February 2024 update

An aerial view of the progress on the Grantham Southern Relief Road.

The latest update on the Grantham Southern Relief Road.

What we achieved in January

Phase Three

  • West side of site – continued steelwork assembly / installed permanent formwork and cantilever formwork
  • East side of site – second base pour for east concrete abutment / concrete south wing wall base / reinforce and shuttering to north wingwall base / connect temporary decking to Pier 5

What's happening in February

Phase Three

  • West side of site – reinforce fixing on bridge deck / installation of cantilever formwork
  • East side of site – concrete east abutment main base / reinforce and shuttering to north wingwall base / concrete north wingwall base / being backfilling east abutment base / connect temporary structure decking and reinforcement to Pier 5 / shutting, concrete pier base and reinforcement to Pier 6 base

Current/ongoing traffic restrictions and closures

  • Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site

Upcoming traffic restrictions and closures

  • N/A

Published: 5th February 2024