A16 Springfield Roundabout March update

Aerial view of the progress on Springfield roundabout

The latest update on the A16 Springfield Roundabout.

What we achieved in February

  • Continued earthworks in the northeast and southwest corners
  • Finished kerbing and drainage in the northeast and southwest corners
  • Constructed new carriageway on the northeast and southwest corners
  • Installed street lighting ducting
  • Started topsoiling the verges

What’s happening in March

  • Complete earthworks and verges in the northeast and southwest
  • Switch over to working in the northwest and southeast areas of site
  • Start earthworks and drainage in the northwest and southeast corners
  • Start BT diversion in the southeast corner

Current/ongoing traffic restrictions and closures

  • 24/7 barriers at the roundabout, with the current two-lane entries and single-lane exits
  • Ongoing narrowed roundabout lanes

Upcoming traffic restrictions and closures

  • N/A

Published: 4th March 2024