Grantham Southern Relief Road March 2024 update

Aerial view of the Grantham Southern Relief Road.

The latest update on the Grantham Southern Relief Road.

What we achieved in February

Phase Three

  • West side of site – reinforced fixing on bridge deck / installed of cantilever formwork / concreted bearing plinths

  • East side of site – concreted east abutment main base / reinforcement and shuttering to north wingwall base / concreted north wingwall base / started backfilling east abutment base / reinforcement and temporary decking to Pier 5 / shuttering and reinforcement to Pier 6 base

What's happening in March

Phase Three

  • West side of site – concrete corbels on western bankseat / install bridge launch equipment
  • East side of site – complete backfill to east abutment base / begin formwork to east abutment / shuttering and concreting Pier 5 crosshead / concrete and begin backfilling to Pier 6 base

Current/ongoing traffic restrictions and closures

  • Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site

Upcoming traffic restrictions and closures

  • N/A

Published: 6th March 2024