Lincoln Eastern Bypass update – Heighington Road re-opened

Heighington Road Bridge

The new 33-metre long Heighington Road bridge above the bypass opened to traffic on Friday 31 January.

What we achieved in January

  • Installed footpath fencing, removed street lighting and planed existing road surface along Hawthorn Road
  • Carried out enabling works ahead of roundabout construction at Washingborough Road
  • Built compound and excavated east base for Greetwell footbridge
  • Continued deck and wing wall construction, along with grouting the permanent bearings for the River Witham Viaduct
  • Continued bank seat works and prepared for delivery of beams for South Delph footbridge superstructure
  • Completed essential kerbing and surfacing works to new Heighington Road bridge
  • Re-open Heighington Road
  • Completed wing wall construction and waterproofing for Lincoln Road underpass
  • Completed base backfill and constructed temporary working platforms for Bloxholm Lane footbridge
  • Continued post-excavation archaeological reporting

What's happening in February

  • Remove kerbs and footways at St Augustine Road
  • Remove street lighting, plane out existing asphalt and begin earthworks and drainage works at Washingborough Road
  • Begin drainage works between Washingborough Road and Heighington Road
  • Begin filter drain installation between Lincoln Road and Sleaford Road
  • Off-site fabrication of permanent parapets for Hawthorn Road footbridge
  • Construct and backfill bases for Greetwell footbridge
  • Continue installing rebar and shuttering and begin concreting to deck and wing walls for River Witham Viaduct
  • Delivery, fabrication and lifting of  bridge deck for South Delph footbridge superstructure
  • Begin backfill to Lincoln Road underpass
  • Continue abutment and wing wall works for Bloxholm Lane footbridge
  • Continue post-excavation archaeological reporting

Upcoming traffic restrictions and closures

  • Full 24/7 closure of Washingborough Road starting Monday 17 February
  • Full 24/7 closure of St Augustine Road starting Monday 17 February

Current/ongoing traffic restrictions and closures

  • Full 24/7 closure of Hawthorn Road from Monday 27 January
  • Full 24/7 closure of Bloxholm Lane and Greetwell Fields Lane
  • Temporary speed restrictions on Washingborough Road, Greetwell Road, Lincoln Road, Sleaford Road and Hawthorn Road
  • Temporary 200m path diversion on the Sustrans route along the River Witham

Published: 3rd February 2020