Brayford Way Bridge and Campus Way ramp improvements set for early April

Campus Way and Brayford Diversion

Works to replace the worn out carriageway on Campus Way ramp and bridge joints on Brayford Way Bridge will start on Monday 6 April.


Improvements temporarily postponed - 01/04/2020

Please note that improvements to Brayford Way Bridge and the Campus Way ramp have been temporarily postponed and are now expected to start in July.

Cllr Richard Davies, executive member for highways, said: "Following a meeting with the contractor, who was unable to guarantee staff levels due to coronavirus, we've decided to temporarily postpone these works until summer.

"I want to reassure residents that we will continue providing essential highway maintenance services during this trying time to keep the county's roads safe for key workers and those making necessary journeys."


Brayford Way Bridge and Campus Way ramp improvements set for early April - 21/02/2020

The total project is expected to last for up to two weeks, Monday to Friday, subject to suitable weather.

A full closure Brayford Way bridge and the Campus Way ramp will be in place from 8pm to 6am each weekday (except Easter Friday and Easter Monday).

The diversion route for northbound traffic at the University Roundabout is via Ropewalk / East-West Link Road / Cross Street / Portland Street / Pelham Bridge / Wigford Way / Newland / Carholme junction.

The diversion route for southbound traffic at the Carholme junction is via Newland / Wigford Way / Pelham Bridge / Kesteven Street / East-West Link Road / University Roundabout.

Access to Campus Way via Brayford Way Bridge will be maintained as far as reasonably practicable. However, during certain works this won't be possible.

In addition, Campus Way residents are encouraged to find alternative parking locations to avoid problems getting vehicles in and out of the works zone after 7pm.

Cllr Richard Davies, Executive Member for highways, said: "Not only will we be rebuilding the Campus Way ramp down to the mini-roundabout, but we're also taking the opportunity to replace two of four bridge joints on the Brayford Way bridge.

"We know the bridge is one Lincoln's most used routes, so we'll be doing everything we can to keep disruption to an absolute minimum.

"This includes carrying all works out overnight and working hard to complete the project earlier than planned."

For up-to-date information about this and other roadworks, visit www.lincolnshire.gov.uk/roadworks.

Published: 21st February 2020