An overview of progress on the Pinchbeck Roundabout improvement project.
What we achieved in January
- Completed construction of the splitter islands
- Prepared for and started laying final road surfacing on Pinchbeck Roundabout and the A16 towards Springfield Roundabout under night-time road closures
- Completed outstanding earthworks and installation of new traffic signs
- Comtinued site clearance
- Completed installation of and tested all new lighting columns
What’s happening in February
- Continue laying new surfacing on Pinchbeck Roundabout and the A16 towards Springfield Roundabout under night-time road closures
- Begin footpath works near Springfield shopping centre
- Install asphalt plug/mechanical and buried joints along A16 from Pinchbeck Roundabout to Springfield Pinchbeck Roundabout
- Install the remaining vehicle restraint system infrastructure / install fencing / lay road markings / begin landscaping at Pinchbeck Roundabout
Current/ongoing traffic restrictions and closures
- Ongoing narrowed lanes on A16 in the roundabout and all its approaches
- Ongoing night-time closure of the roundabout, all its legs and sections of the A16 until mid-March, weekday evenings only, 8pm to 6am (subject to weather)
Upcoming traffic restrictions
- Footpath closure from the A151 (adjacent to Coronation Channel) as and when required
- Temporary closure of the northern footway on A151 Holbeach Road as needed
- The diversion route for pedestrians will be on the opposite side of carriageway
For more information about this and other major highways projects, visit www.lincolnshire.gov.uk/majorprojects.