A16 Pinchbeck Roundabout February 2025 update

Pinchbeck Roundabout - Jan 2025 1

An overview of progress on the Pinchbeck Roundabout improvement project.

What we achieved in January

  • Completed construction of the splitter islands
  • Prepared for and started laying final road surfacing on Pinchbeck Roundabout and the A16 towards Springfield Roundabout under night-time road closures
  • Completed outstanding earthworks and installation of new traffic signs
  • Comtinued site clearance
  • Completed installation of and tested all new lighting columns

What’s happening in February

  • Continue laying new surfacing on Pinchbeck Roundabout and the A16 towards Springfield Roundabout under night-time road closures
  • Begin footpath works near Springfield shopping centre
  • Install asphalt plug/mechanical and buried joints along A16 from Pinchbeck Roundabout to Springfield Pinchbeck Roundabout
  • Install the remaining vehicle restraint system infrastructure / install fencing / lay road markings / begin landscaping at Pinchbeck Roundabout

Current/ongoing traffic restrictions and closures

  • Ongoing narrowed lanes on A16 in the roundabout and all its approaches
  • Ongoing night-time closure of the roundabout, all its legs and sections of the A16 until mid-March, weekday evenings only, 8pm to 6am (subject to weather)

Upcoming traffic restrictions

  • Footpath closure from the A151 (adjacent to Coronation Channel) as and when required
  • Temporary closure of the northern footway on A151 Holbeach Road as needed
  • The diversion route for pedestrians will be on the opposite side of carriageway

For more information about this and other major highways projects, visit www.lincolnshire.gov.uk/majorprojects.

Funded by Uk Gov Logo

Published: 3rd February 2025