Grantham Southern Relief Road February 2025 update

GSRR - Jan 2025 1

An overview of progress on the Grantham Southern Relief Road project.

What we achieved in January

  • East side of site – grout bearings into position for span 7 / remove temporary works from beneath the bridge beams / began formwork, reinforcement and concrete works to complete the ballast walls and wingwalls

What's happening in February

  • East side of site – continue formwork, reinforcement and concrete works to complete the ballast walls and wingwalls

Current/ongoing traffic restrictions and closures

  • Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site

Upcoming traffic restrictions and closures

  • N/A

For more information about this and other major highways projects, visit www.lincolnshire.gov.uk/majorprojects.

Funded by GL LEP Midlands Engine logo

Published: 3rd February 2025