An overview of progress on the Sincil Bank project.
What we achieved in January
- Installed new kerbs and resurfaced the footway on both sides of Sincil Bank from Kirkby Street to Scorer Street
- Started excavations for two new build-outs and installed new pedestrian crossings near Scorer Street, Hood Street and Sausthorpe Steet
- Relayed channel blocks from Kirkby Street to Scorer Street
- Resurfaced carriageway from Kesteven Street to Ripon Street
What’s happening in February
- Replace kerbs and install new footways on both sides of Sincil Bank from Sausthorpe Street to football ground car park
- Replace existing pedestrian crossing south of Sausthorpe Street
- Carry out additional drainage works
- Resurface from Ripon Street to football ground
- Begin footway and carriageway resurfacing at football ground
Current/ongoing traffic restrictions and closures
- 24/7 road closure on Sincil Bank, from Ripon Street to Sausthorpe Street
- Diversion route is via Cross Street
Upcoming traffic restrictions and closures
- Parking restrictions from Ripon Street to Sausthorpe Street
For more information about this and other major highways projects, visit www.lincolnshire.gov.uk/majorprojects.