Sincil Bank improvements February 2025 update

Sincil Bank - Jan 2025 1

An overview of progress on the Sincil Bank project.

What we achieved in January

  • Installed new kerbs and resurfaced the footway on both sides of Sincil Bank from Kirkby Street to Scorer Street
  • Started excavations for two new build-outs and installed new pedestrian crossings near Scorer Street, Hood Street and Sausthorpe Steet
  • Relayed channel blocks from Kirkby Street to Scorer Street 
  • Resurfaced carriageway from Kesteven Street to Ripon Street

What’s happening in February

  • Replace kerbs and install new footways on both sides of Sincil Bank from Sausthorpe Street to football ground car park
  • Replace existing pedestrian crossing south of Sausthorpe Street
  • Carry out additional drainage works 
  • Resurface from Ripon Street to football ground
  • Begin footway and carriageway resurfacing at football ground 

Current/ongoing traffic restrictions and closures

  • 24/7 road closure on Sincil Bank, from Ripon Street to Sausthorpe Street
    • Diversion route is via Cross Street 

Upcoming traffic restrictions and closures

  • Parking restrictions from Ripon Street to Sausthorpe Street

For more information about this and other major highways projects, visit www.lincolnshire.gov.uk/majorprojects.

Funded by Uk Gov Logo

Published: 3rd February 2025