An overview of progress on the Grantham Southern Relief Road project.
What we achieved in April
- West side of site – installed drain run and associated gullies at Honda Roundabout
- East side of site – continued formwork, reinforcement and concrete works to the eastern abutment / shuttering and concreting to north wingwall for pour two / shuttering to south rear wingwall / concrete finishing to wingwalls
What's happening in May
- West side of site – lay kerbing at the Honda Roundabout pond access / install gabions to Pond B
- East side of site – backfill and bowed wall drainage to the east abutment / excavate the working platform from behind the east abutment / complete the Narrow Filter drain to at the east embankment / lay sub-base at the backfilled area of the east abutment
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
- N/A