An overview of progress on the Grantham Southern Relief Road project.
What we achieved in May
- West side of site – started installing Pond 3 gabions / installed drainage around the face of the west embankment / installed ducting to Spittal Gate roundabout pond access road
- East side of site – began backfilling and drainage to east abutment / completed narrow filter drain to the constructed east embankment as far as possible
What's happening in June
- West side of site – complete pond access roadworks at Spittal Gate roundabout / install drainage around Pond B in current haul road
- East side of site – complete backfilling to east embankment
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
- N/A