Grantham Southern Relief Road June 2025 update

GSRR Drone - June 2025

An overview of progress on the Grantham Southern Relief Road project.

What we achieved in May

  • West side of site – started installing Pond 3 gabions / installed drainage around the face of the west embankment / installed ducting to Spittal Gate roundabout pond access road
  • East side of site – began backfilling and drainage to east abutment / completed narrow filter drain to the constructed east embankment as far as possible

What's happening in June

  • West side of site – complete pond access roadworks at Spittal Gate roundabout / install drainage around Pond B in current haul road
  • East side of site – complete backfilling to east embankment

Current/ongoing traffic restrictions and closures

  • Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site

Upcoming traffic restrictions and closures

  • N/A

Published: 2nd June 2025