Improvements in Whaplode Drove will start in mid-June.
Karen Cassar, assistant director for highways, said: “Hull’s Drove, either side of the Martins Road junction, is in a dire state so we’ll be completely rebuilding this section of B1166 starting next month.
“This will be a major piece of engineering, with the team expecting to use over 2,000 tonnes of asphalt and other road-building materials to complete the job.
“While on-site, we’ll also be stabilising the B1166 verge to the west of the Martins Road junction, as well as improving the road surface further Hull’s Drove near the A16 junction.
“Like any major roadworks, there will be some disruption which we will do our best to keep to a minimum.”
Dates and timeframes
Monday 16 June for up to four weeks
Location of works
Maintenance surfacing – on the B1166 near the A16 junction access (no works to the junction itself)
Verge stabilisation – western section of the B1166 near the Martins Road junction
Road reconstruction – B1166, 130m on both sides of the Martin’s Road junction; and 40m of the Martins Road junction
Phasing of works
Phase 1 – maintenance surfacing and verge stabilisation for up to one week
Phase 2 – reconstruction of the B1166 and a 40m section of Martins Road for up to three weeks
Traffic management
24/7 road closure on B1166 Hull’s Drove (from near the A16 junction to near the Dowsdale Bank junction) and the Martins Road junction for the whole of the project (access will be maintained for residents)
Diversion route
Via B1166 / B1168 / B1165 / B1357 / A16, and vice versa
Karen Cassar added: “We'll be doing everything we can during the works to keep disruption to a minimum, including maintaining access for residents and emergency vehicles during our working hours.