Grantham Southern Relief Road July update

GSRR Drone - June 2025

An overview of progress on the Grantham Southern Relief Road project.

What we achieved in June

  • West side of site – completed ducting, drainage and kerbing works to the pond access road / completed drainage around Pond B
  • East side of site – completed backfilling to the east abutment / started installing drainage to ch 800 and 900

What's happening in July

  • West side of site – complete pond access roadworks at Spittal Gate roundabout / install drainage around Pond B in current haul road
  • East side of site – complete drainage the east embankment / install concrete channel to east embankment

Current/ongoing traffic restrictions and closures

  •  Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site

Upcoming traffic restrictions and closures

  • N/A

Published: 1st July 2025