An overview of progress on the Grantham Southern Relief Road project.
What we achieved in June
- West side of site – completed ducting, drainage and kerbing works to the pond access road / completed drainage around Pond B
- East side of site – completed backfilling to the east abutment / started installing drainage to ch 800 and 900
What's happening in July
- West side of site – complete pond access roadworks at Spittal Gate roundabout / install drainage around Pond B in current haul road
- East side of site – complete drainage the east embankment / install concrete channel to east embankment
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
- N/A