Grantham Southern Relief Road August update

Grantham Southern Relief Road - Drone July 2025

An overview of progress on the Grantham Southern Relief Road project.

What we achieved in July

  • West side of site – completed pond access road works at Spittal Gate roundabout / installed drainage around Pond B in current haul road / cut off shear studs, ready for strengthening plates
  • East side of site – complete drainage and install concrete channel to east embankment

What's happening in August

  • West side of site – remove and replace trestle supports at the bridge launch area, including jacking up the beams to remove the supports beneath / carry out surfacing to the access track at Spittal Gate roundabout
  • East side of site – trim Type 1 and lay surfacing up to binder course to east embankment

Current/ongoing traffic restrictions and closures

  • Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site

Upcoming traffic restrictions and closures

  • N/A

Published: 1st August 2025