An overview of progress on the Carholme Road improvement project.
What we achieved in July
- Removed blockages and cleared debris within the drainage system on Carholme Road
- Installed new LCC surface water drainage gullies and laterals within Phase 1 (Westfield Street to Gresham Street)
- Carried out carriageway resurfacing and replaced road markings on Staunton Street and Staunton Court
- Started drainage, kerbing and footway works on Gresham Street
- Started drainage works within Phase 2 (Gresham Street to Roman Wharf) installing new LCC Surface water drainage Gullys and laterals
- Ironworks reinstatement and repairs
What’s happening in August
- Night-time carriageway resurfacing works on Carholme Road for Phases 1 and 2
- Complete Gresham Street improvement works
- Footway resurfacing in localised areas throughout the site
- Install new LCC surface water drainage gullies and laterals within Phase 2 (Gresham Street to Roman Wharf)
- Reinstate and repair ironworks
Current/ongoing traffic restrictions and closures
- Narrowed lanes and temporary traffic signals on weekdays throughout the project
- Road closure on Gresham Street until 4th August
Upcoming traffic restrictions and closures
- Narrowed lanes and temporary traffic signals on weekdays throughout the project
- Night-time road closures from 7pm-6am within Phase 1 starting w/c 4th August for up to two weeks
- Night-time road closures from 7pm-6am within Phase 2 starting w/c 18th August for up to three weeks
Please note that our public liaison officer will be in touch with residents and businesses affected closer to the time of the road closures with further updates.
Project phasing
- Phase 1: just past Nelson Street to just past Charlesworth Street
- Phase 2: just past Charlesworth Street to just past Roman Wharf
- Phase 3: just past Roman Wharf to just past Severn Street
- Phase 4: just past Severn Street to just past the golf club
For more information about this project, please visit www.lincolnshire.gov.uk/carholmeroad.