An overview of progress on the Grantham Southern Relief Road project.
What we achieved in September
- West side of site – replaced trestles under bridge / began launch nose installation / constructed access stairs to the west embankment
- East side of site – completed surfacing up to binder course on the east embankment / topsoiled verges to the east embankment / installed safety barrier to the east embankment
What's happening in October
- West side of site – continue launch nose installation / fix reinforcement to the deck / replace plywood to the cantilever formwork
- East side of site – install remaining street lights to the mainline and repair the chevron sign at the roundabout
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
- N/A