Grantham Southern Relief Road October update

GSRR October 2025

An overview of progress on the Grantham Southern Relief Road project.

What we achieved in September

  • West side of site – replaced trestles under bridge / began launch nose installation / constructed access stairs to the west embankment
  • East side of site – completed surfacing up to binder course on the east embankment / topsoiled verges to the east embankment / installed safety barrier to the east embankment

What's happening in October

  • West side of site – continue launch nose installation / fix reinforcement to the deck / replace plywood to the cantilever formwork
  • East side of site – install remaining street lights to the mainline and repair the chevron sign at the roundabout

Current/ongoing traffic restrictions and closures

  • Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site

Upcoming traffic restrictions and closures

  • N/A

Published: 6th October 2025