An overview of progress on the Grantham Southern Relief Road project.
What we achieved in October
- West side of site – continued launch nose installation / fixed reinforcement to the deck / replaced plywood to the cantilever formwork
- East side of site – installed remaining street lights to mainline and repaired chevron sign at the roundabout
What's happening in November
- West side of site – install scaffolds for welding works / begin welding of launch nose / begin installation of launch equipment / weld plate stiffeners to beams
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
- N/A