Grantham Southern Relief Road December update

GSRR - Nov 2025

An overview of progress on the Grantham Southern Relief Road project.

What we achieved in November

•    West side of site – installed scaffolds for welding works / began welding of launch nose / started installation of launch equipment / welded plate stiffeners to beams

What's happening in December

•    West side of site – continue welding operations / remove scaffolds / install heavy-lifting equipment

Current/ongoing traffic restrictions and closures

•    Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site

Upcoming traffic restrictions and closures

•    N/A
 

Published: 1st December 2025