An overview of progress on the Grantham Southern Relief Road project.
What we achieved in November
• West side of site – installed scaffolds for welding works / began welding of launch nose / started installation of launch equipment / welded plate stiffeners to beams
What's happening in December
• West side of site – continue welding operations / remove scaffolds / install heavy-lifting equipment
Current/ongoing traffic restrictions and closures
• Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
• N/A