The closures are allowing Galliford Try to carry out piling works for the new bridged junction.
What we achieved in April
- Continued bored piling works to firm the abutment and wingwalls of the new underpass
- Continued earthworks to the western and eastern roundabouts and slip roads, including lime modification
- Commenced piling works adjacent to the northbound A1
- Continued archaeological works for Phase Three east of the railway
What's happening in May
- Complete bored piling works to the western half of the new underpass
- Continue earthworks to the western and eastern roundabouts and slip roads, including lime modification
- Begin drainage works for the western and eastern roundabouts
- Complete bored piling works and install temporary sheet piling adjacent to the northbound A1
- Continue final archaeological works and carry out ground surveys and trial holes for Phase Three
Upcoming traffic restrictions and closures
- None confirmed beyond May
Current/ongoing traffic restrictions and closures
- Full night-time lane closure on the northbound A1 between Little Ponton and Harlaxton on weekday evenings (M-F) from 8pm to 6am until Wednesday 20 May
- Diversion route via A606 at Stamford to A607 to A1 at Harlaxton
- No closure on Friday 8 May due to bank holiday - 50mph speed limit and narrow lanes on the A1 between Harlaxton to Little Ponton