An overview of progress on the Grantham Southern Relief Road project.
What we achieved in January
West side of site – installed temporary works to Pier 2 / equipment tests
What's happening in February
West side of site – install temporary works to Pier 3 / maintenance for working platform at Pier 2 and 3
Current/ongoing traffic restrictions and closures
Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
N/A