Additional footway/cycleway works required on Hawthorn Road

A road closed sign.

Two weeks of repairs will be carried out in April.

Sam Edwards, head of highways infrastructure, said: “We always carry out tests to ensure newly-laid surfacing meets the high standards we expect.  

“Unfortunately, in this instance, the asphalt hasn’t met our stringent requirements and the underground weed barrier is not strong enough to contain the invasive weeds growing underneath. The combination of these two things has led to cracks forming, subsidence occurring, and weeds growing out from the new footway/cycleway. 

“As a result, the contractor will be replacing the affected surfacing as part of our contract with them, at their own cost. As part of those works, we’ll also be taking the opportunity to treat the invasive weeds and install a stronger weed barrier.

“Acting now means we can stop the pathway breaking down because of the invasive weeds, which will mean more pleasant and safer walks for people in the area in the long term.”

Dates and timeframes

Tuesday 7 April for up to two weeks

Location of works

Southern side: Hawthorn Road, between the Lincoln Eastern Bypass and Cherry Paddocks

Northern side: Hawthorn Road, opposite Cherry Paddocks and Hawthorn Avenue

Traffic management

Southern side: 24/7 road closure on Hawthorn Road (pedestrian access will be maintained)

Northern side: daytime lane closure and temporary traffic signals

Diversion route

Via Kennel Lane / A158 / Lincoln Eastern Bypass, and vice versa


Sam Edwards continued: “Repairing these defects now will not only save the council money and time in the future, but it will prevent further disruption in the future.

“Because these works will inevitably cause some disruption, I want to thank everyone in advance for bearing with us.”

For up-to-date information about this and other roadworks, visit www.lincolnshire.gov.uk/roadworks.

Published: 12th March 2026