Grantham Southern Relief Road May update

GSRR Drone - 200326

An overview of progress on the Grantham Southern Relief Road project.

What we achieved in April

  • Installed steelwork for shunt 2 of the bridge, including installing 4x pairs of main girders (60-80t each), cross girders and maintenance access gantry
  • Installed of launch tail for shunt 2 
  • Commenced installation of permanent formwork and cantilever falsework to the deck for shunt 2
  • Continued installation of temporary works to Pier 3 for shunt 2

What's happening in May

  • Continue installation of permanent formwork, cantilever formwork and commence deck rebar installation
  • Commence preparation of launch equipment for shunt 2
  • Continue temporary works installation to Piers 2, 3 and 4

Current/ongoing traffic restrictions and closures

  • Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site.

Upcoming traffic restrictions and closures

  • N/A

For the latest news on the Grantham Southern Relief Road, visit www.lincolnshire.gov.uk/gsrr.

Published: 5th May 2026