Grantham Southern Relief Road June update

GSRR Drone - March 2026 (3)

An overview of progress on the Grantham Southern Relief Road project.

What we achieved in May

  • Fixed reinforcement to the bridge deck
  • Completed installation of cantilever formwork to the bridge deck
  • Installed temporary works to Pier 3

What's happening in June

  • Install 60.5 metre supports to Piers 2 and 3
  • Prepare for launch of bridge to Pier 2 this summer

Current/ongoing traffic restrictions and closures

  • Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site.

Upcoming traffic restrictions and closures

  • N/A

Published: 3rd June 2026