An overview of progress on the Grantham Southern Relief Road project.
What we achieved in May
- Fixed reinforcement to the bridge deck
- Completed installation of cantilever formwork to the bridge deck
- Installed temporary works to Pier 3
What's happening in June
- Install 60.5 metre supports to Piers 2 and 3
- Prepare for launch of bridge to Pier 2 this summer
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site.
Upcoming traffic restrictions and closures
- N/A