Grantham Southern Relief Road - August 2026 update

Grantham Southern Relief Road - August 2026

An overview of progress on the Grantham Southern Relief Road project.

What we achieved in July

West side of site

  • Moved 60.5m support to Pier 4
  • Installed structural steelwork to the rear of the bridge deck
  • Began installation of Omnia permanent formwork and reinforcement to the deck
  • Started installation of cantilever formwork and launch tail

East side of site

  • Started Installation of Temporary Works To Pier 4

What's happening in August

West side of site

  • Complete installation of permanent formwork and cantilever formwork
  • Continue fixing reinforcement
  • Begin Shunt 3, moving the launch nose onto Pier 3

East side of site

  • Install Ancillary supports at Pier 4

Current/ongoing traffic restrictions and closures

  • Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site

Upcoming traffic restrictions and closures

  • N/A

Published: 3rd August 2026