An overview of progress on the Grantham Southern Relief Road project.
What we achieved in July
West side of site
- Moved 60.5m support to Pier 4
- Installed structural steelwork to the rear of the bridge deck
- Began installation of Omnia permanent formwork and reinforcement to the deck
- Started installation of cantilever formwork and launch tail
East side of site
- Started Installation of Temporary Works To Pier 4
What's happening in August
West side of site
- Complete installation of permanent formwork and cantilever formwork
- Continue fixing reinforcement
- Begin Shunt 3, moving the launch nose onto Pier 3
East side of site
- Install Ancillary supports at Pier 4
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
- N/A