An overview of progress on the Grantham Southern Relief Road project.
What we achieved in August
West side of site
- Completed assembly of the superstructure, ready to commence Shunt 3
- Continued assembly of access gantry
- Started Shunt 3, covering 25 metres from pier 2 to pier 3
- Removal of temporary work supports at pier 3
- Pier 4 installation of temporary works for launch
East side of site
- Street lighting connection works
What's happening in September
West side of site
- Continue shunt 3 across East Coast Mainline through to Pier 4
- Commence removal of launch equipment in launch area
- Complete assembly of access gantry
East side of site
- Pier 4 monitoring installation
- Removal of temporary work supports at pier 4
- Install Launch temporary works to Pier 5
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
- N/A