Grantham Southern Relief Road - October 2026 update

Grantham Southern Relief Road -  September 2026

An overview of progress on the Grantham Southern Relief Road project.

What we achieved in September

West side of site

  • Continued assembly of access gantry
  • Carried out Shunt 3 from pier 3 to pier 4, which was roughly 70m
  • Continued removal of launch equipment in launch area

East side of site

  • Removal of temporary work supports at pier 4 under night-time works
  • Installation of temporary works to Pier 5

What's happening in October

West side of site

  • Complete assembly of access gantry
  • Continue removal of launch equipment in launch area

East side of site

  • Continue shunt 3 across East Coast Mainline through to Pier 5 under night-time works
  • Commence removal of bridge launch nose
  • Launch temporary works to Pier 5
  • Begin removal of Span 5 temporary plates

Current/ongoing traffic restrictions and closures

  • Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site

Upcoming traffic restrictions and closures

  • N/A

Published: 2nd October 2026