Grantham Southern Relief Road - November 2026 update

Grantham Southern Relief Road - Bridge Building - Oct 2026

An overview of progress on the Grantham Southern Relief Road project.

What we achieved in October

West side of site

  • Completed the bridge launch 
  • Continued removal of launch equipment in launch area
  • Continued assembly of access gantry

East side of site

  • Continued installation of temporary works to Pier 5
  • Removed sections of the temporary work launch nose

What's happening in November

West side of site

  • Complete assembly of access gantry
  • Continue removal of launch equipment in launch area
  • Commence bulk earthworks fill to embankment (over 100,000 tonnes to be used)

East side of site

  • Launch temporary works removal to Pier 5
  • Continue removal of Span 5 temporary strengthening plates
  • Move fill material from allotment to west embankment

Current/ongoing traffic restrictions and closures

  • Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site

Upcoming traffic restrictions and closures

  • N/A

Published: 2nd November 2026