An overview of progress on the Grantham Southern Relief Road project.
What we achieved in October
West side of site
- Completed the bridge launch
- Continued removal of launch equipment in launch area
- Continued assembly of access gantry
East side of site
- Continued installation of temporary works to Pier 5
- Removed sections of the temporary work launch nose
What's happening in November
West side of site
- Complete assembly of access gantry
- Continue removal of launch equipment in launch area
- Commence bulk earthworks fill to embankment (over 100,000 tonnes to be used)
East side of site
- Launch temporary works removal to Pier 5
- Continue removal of Span 5 temporary strengthening plates
- Move fill material from allotment to west embankment
Current/ongoing traffic restrictions and closures
- Lane restrictions around the B1174 Roundabout to facilitate the construction of the haul route and access into site
Upcoming traffic restrictions and closures
- N/A