Lincoln Eastern Bypass update: Lincoln Road roundabout officially opens

LEB Branston roundabout from above
Lincoln Eastern Bypass roundabout at Branston

Road users can now drive on the first of four Lincoln Eastern Bypass roundabouts.

What we achieved in August

  • Completed construction of and opened Lincoln Road roundabout
  • Completed walls for Lincoln Road underpass
  • Steel beams assembled and delivered on south side of river for River Witham Viaduct
  • Completed concreting of columns for River Witham Viaduct
  • Completed offsite fabrication and painting of steel Hawthorn Road footbridge superstructure
  • lifted bridge beams into place for Heighington Road bridge
  • Started erecting rebar  for Heighington Road bridge deck
  • Continued drainage between Greetwell Road & Wragby Road and Branston brook & Heighington Road
  • Continued sub-base, gullies and kerbings between Sleaford Road and Lincoln Road
  • Continued post-excavation archaeological reporting

What's happening in September

  • Construct reinforced concrete  roof slab and excavate/construct wall bases for Lincoln Road underpass
  • Receive delivery of and assemble steel beams at north side of river for River Witham Viaduct
  • Complete platforms for steelwork crane, complete bearing plinths, complete north and south abutments and prepare for beam lifting for River Witham Viaduct
  • Prepare for delivery of steel Hawthorn Road footbridge superstructure and lift into place
  • Begin excavation of bases for Bloxholm Lane footbridge
  • Continue construction of Heighington Road bridge, including construction of the bridge deck
  • Begin drainage, street lighting, earthworks and surfacing at Wragby Road roundabout
  • Continue drainage works between Greetwell Road and Wragby Road; Washingborough Road and Greetwell Road; and Branston Brook to Heighington Road
  • Continue sub-base, gullies and kerbings between Sleaford Road and Lincoln Road
  • Begin drainage, street lighting, earthworks and surfacing at Sleaford Road roundabout
  • Continue post-excavation archaeological reporting

Upcoming traffic restrictions and closures

  • Three-way, night-time traffic signals on Wragby Road roundabout from 9 September to 15 November
  • 24-hour, three-way traffic signals on Wragby Road roundabout from 23-29 September
  • Lane closure on Wragby Road roundabout from 7-20 October
  • Weekend-only road closure on A15 Sleaford Road from 6am on Saturday to 6am on Monday on 6-9 September, 13-16 September, 20-23 September and 27-30 September – along with the following ten weekends

Current/ongoing traffic restrictions and closures

  • Temporary speed restrictions on Washingborough Road, Greetwell Road, Lincoln Road, Sleaford Road and Hawthorn Road
  • Weekday off-peak two-way traffic signals (9:30am – 3:30pm) until mid-December on A15 Sleaford Road
  • Temporary traffic signals on Hawthorn Road, Greetwell Road, Washingborough Road and Lincoln Road to allow safe access for construction vehicles and machinery
  • Temporary 200m path diversion on the Sustrans route along the River Witham
  • Full closure of Heighington Road, Bloxholm Lane and Greetwell Fields Lane

Published: 6th September 2019