Sleaford Rugby Club Junction update – Works approach midway point

Sleaford Rugby Club

Building upon the works carried out in July will be the main focus this month.

What we achieved in July

  • Completed construction of the culvert and headwalls / started construction of the embankment, kerbs and drainage for the A17 slip road
  • Completed kerbing, drainage and footway construction (except final surfacing) on the west side of the A153
  • Completed traffic signal ducting, kerbing and base-level surfacing course on the northern traffic island
  • Commenced kerbing, drainage and installing traffic signal equipment on the southern island
  • Commenced excavation, kerbing and drainage on the east side of the A153
  • Completed BT ducting and box construction ahead of upcoming BT cable diversion
  • Reconstructed the carriageway on the A17 entry slip lane

What's happening in August

  • Complete the construction of the embankment, kerbs and drainage to the A17 slip road
  • Complete kerbing, drainage and traffic signal equipment on the southern island
  • Complete excavation, kerbing, drainage and footway / remove and dispose existing kerbing and drainage on the east side of the A153
  • Complete streetlight column installation on the west side of the A153
  • Continue WPD and BT utility works
  • Commence construction of two new central traffic islands

Current/ongoing traffic restrictions and closures

  • Full 24/7 closure of eastbound A17 exit slip road
  • Right-turn ban off of the A153 onto the A17
  • Temporary 30mph speed restriction and narrowed lane on A153 East Road

Upcoming traffic restrictions and closures

  • Two-way traffic signals (occasional weekend/off- peak usage when required)

Published: 3rd August 2020