The new Washingborough Road roundabout is now complete.
What we achieved in August
- Officially opened the new Washingborough Road roundabout / completed road surfacing, footways, pond lining and road lining for the new roundabout
- Continued drainage, street lighting, kerbing, fence installation and road surfacing between Wragby Road to Greetwell Road
- Continue drainage works between Greetwell Road to Washingborough Road
- Began installation of permanent parapets for Hawthorn Road footbridge
- Delivered and lifted bridge deck into place / completed backfill for Greetwell footbridge
- Completed backfill / installed kerb and drainage units / continued wing walls for River Witham Viaduct
- Complete finishing works for South Delph footbridge
- Completed Hawthorn retaining wall
- Continue deck waterproofing / installed metal access walkways at Market Rasen Line rail bridge deck
- Delivered and lifted bridge deck into place for Bloxholm Lane footbridge
What's happening in September
- Complete drainage, street lighting, kerbing, fence installation and road surfacing between Wragby Road to Greetwell Road
- Continue drainage works / begin kerbing, pond lining and road surfacing between Greetwell Road to Washingborough Road
- Complete retention pond near new Washingborough Road roundabout
- Begin footway edging and surfacing between Washingborough and Lincoln Road (Branston)
- Continue street lighting and traffic signage works at Wragby Road roundabout
- Complete installation of permanent parapets for Hawthorn Road footbridge
- Install metal parapets and construct approach paths for Greetwell footbridge
- Complete wing walls and parapets / continue verge concreting and substructure works for River Witham Viaduct
- Construct approach paths for South Delph footbridge
- Fit metal railings and carry out final concrete works for Lincoln Road Underpass
- Continue deck waterproofing / installed metal access walkways at Market Rasen Line rail bridge deck
- Continue verge concreting / install kerb/drainage units / carry out additional wing wall works at Market Rasen Line rail bridge
- Install metal parapets and construct approach paths for Bloxholm Lane footbridge
Upcoming traffic restrictions and closures
-
Weekend road closures at Lincoln Road (Branston) from 6am Saturday morning until 6am Monday morning (road may be re-opened before 6am on Monday morning, dependant on how the works progress)
- 5-7 September / 12-14 September / 19-21 September / 26-28 September / 3-5 October / 10-12 October
-
Weekend road closures at Greetwell Road from 6am Saturday morning until 6am Monday morning (road may be re-opened before 6am on Monday morning, dependant on how the works progress)
- 19-21 September / 26-28 September / 3-5 October / 10-12 October / 17-19 October / 24-26 October
-
Temporary night-time traffic signals at Wragby Road roundabout from 6:30pm to 6am, Monday to Friday
- Monday 14 September for three weeks
Current/ongoing traffic restrictions and closures
- Full 24/7 closure of Washingborough Road and Hawthorn Road
- Full 24/7 closure of Bloxholm Lane and Greetwell Fields Lane (new Bloxholm link off of Sleaford Road open)
- Temporary speed restrictions on Heighington Road, Greetwell Road, Lincoln Road and Sleaford Road
- Temporary 200m path diversion on the Sustrans route along the River Witham
*Information accurate at time of publication