We have moved over 3,000 tonnes of earth, laid over 1,500 tonnes of tarmac, excavated 275m of new ditches, and lots more.
What we achieved in October
- Installed nearly 220m of new kerb drainage for the new roundabout
- More than 3,000 tonnes of earth moved across site for constructing embankments
- Constructed two new tactile crossings at the new roundabout
- Re-aligned the Horncastle Lane junction to improve drainage and allow more space for vehicles to make the manoeuvres
- Laid over 1,500 tonnes of tarmac for the new roundabout and its Lincoln Road arm
- Complete the installation of 15 new gullies on site
- Installed 300m of new Anglian Water pipes, which will provide the new main feed to Welton and Dunholme
- Installed 100m of new drainage connections and 1km of BT ducting
- Excavated 275m of new ditches
What's happening in November
- Begin construction of new and wider 2.5m shared cycleway/footway
- Complete the installation of the Anglian Water main and a new smaller main near the commercial site
- Continue installing new drainage along the newly-aligned Lincoln Road, including excavating and building 14 new gullies and connections
- Lay an additional 1,500 tonnes of new tarmac throughout the site
- Construct 350m of new kerbing
- Finish installing BT boxes and ducting / connecting cables
Current/Ongoing traffic restrictions and closures
- Temporary 30mph speed limit on the A46
- Full road closure of Lincoln Road Welton until mid-December
- Diversion via Honeyholes Lane / Ryland Road / Lincoln Road Dunholme / A46, and vice versa
- Right-turn ban from A15 onto Heath Lane into Welton and from Heath Lane onto A15 until mid-December
- Temporary traffic signals, as required, from 9:30am to 3:30pm on the A46 from now until mid-December
Upcoming traffic restrictions and closures
- Temporary 24/7 traffic signals on the A46 throughout December 2020