Upcoming works include the commissioning of the new water mains, excavating 1,000 tons of earth, laying of kerbs, and lots more.
What we achieved in December
- Commissioned new BT cables and removed old cables
- Continued drainage works, including building new gullies and manholes
- Laid 1,000 tonnes of new tarmac
- Completed street lighting foundations
What's happening in January
- Commission new Anglian Water mains
- Lay final 80m of kerbing for the new Lincoln Road
- Excavate final 1,000 tonnes of earth for new ditches at Lincoln Road
- Demolish and remove sections of A46 to allow the new roundabout approach to be constructed and the old concrete foundation to be removed
- Lay new kerbs on the A46 from Horncastle Lane to the new roundabout
- Continue drainage works, including building new gullies and manholes
Current/Ongoing traffic restrictions and closures
- Temporary 30mph speed limit on the A46
- Full road closure of Lincoln Road Welton until mid-March
- Diversion via Honeyholes Lane / Ryland Road / Lincoln Road Dunholme / A46, and vice versa
- Right-turn ban from A15 onto Heath Lane into Welton and from Heath Lane onto A15 until mid-March
- Temporary traffic signals, as required, from 9:30am to 3:30pm as required until mid-January
Upcoming traffic restrictions and closures
- Temporary 24/7 traffic signals on the A46 from mid-January 2021 to the end of the works
- Full closure of Horncastle Lane, at its junction with the A46, from 20th January for two months
- Diversion via the A46 to Nettleham Roundabout then to the A46/A15 Riseholme Roundabout; then the A15 to the A15-A1500 Roundabout (which joins with the other end of Horncastle Lane), and vice versa